GWR Route: Banbury to Wolverhampton
Leamington Spa Station: gwrls878
View showing the central portion of the up platform with its
waiting rooms and lavatories which was the first section to be demolished. The
old train shed at the Birmingham end of the platform was used by the contractor
to store both plant, equipment and materials. The demolition work would have
been carried out during 'possession-periods' at weekends, normally starting
late Saturday evening and ending late on Sunday night or very early on Monday
morning in order to avoid possible damage to passing traffic.