|
Stations, Junctions, etc
Engine Sheds
Other
|
|
Harbury Cement Works
Eight miles south of Leamington Spa in the parish of
Bishop's Itchington, Richard Greaves established a Blue Lias Limeplant in 1820,
but when in 1847 Major General Sir Charles Pasley wrote his treatise on cement,
he mentioned that the Greaves Works was one of only three places in the country
producing water cement (a description used for pre-Portland
artificial cement). Following the opening of the Great Western Railway in 1852,
Greaves, Bull and Lakin established a new cement works adjacent to the line in
1855. They claimed to make Portland cement, but the independent consultant
Charles Spackman later wrote that the true product was only made
when a double burning and wet process was adopted by the company in 1864.
With no canal connections the Harbury Works relied on the
railway for importing coal to fuel the kilns and export the final products. It
is known that the Great Western Railway modified the railway connections at
Harbury in 1883 and that a nameplate was ordered for the first Signal Box at
Greaves Siding in July 1899. Further alterations were made to the track in 1907
with the addition of a down goods line and a second connection to the Works.
Possibly as a result of the wartime increase in cement requirements, the
original Signal Box was replaced in February 1918.
There were four bottle kilns in operation by 1882 producing
120 tons of Portland cement per week, but capacity increased with the
introduction of new kiln technology and by 1907 there were eleven Johnson
chamber kilns and seven Batchelor chamber kilns producing 600 tons per week.
The first rotary kiln (A1) was supplied by Krupp and installed in 1909.
Although this 30 foot long kiln almost doubled the works output by producing 78
tons per day, the chamber kilns continued in intermittent operation until a
second longer rotary kiln, supplied by Ernest Newell, was installed in 1912. A
third rotary kiln supplied by Edgar Allen, was installed in 1924 and the two
older kilns were lengthened in the same year. A1 was now 48 foot long, while
both A2 and A3 were 160 foot long. The total capacity of the three rotary kilns
was 343 tons per day. Slurry sprays were successfully installed on the three
kilns in 1926 and this both improved the plants efficiency by about 15%
and also increased emissions of kiln dust into the environment.
In 1927, Harbury Works was purchased by the Allied Cement
Manufacturers (ACM) known as the Red Triangle Group under the
chairmanship of Henry Horne, however within a few years the economic climate
had lead to overcapacity in the cement industry and ACM went bankrupt in 1931.
The cement interests of ACM including Harbury Works were acquired from the
receiver by Associated Portland Cement Manufacturers (APCM) in April 1932. APCM
is best known as the owner of the 'Blue Circle' cement brand. Immediately after
taking over the Harbury Works the slurry spraying in kiln A3 was replaced with
a chain system and in 1938 a desiccator was added. Kilns A1 and A2 were also
replaced with newer second-hand kilns from Ellesmere Port in 1933, and Burham
in 1937, being renamed B1 and B2 respectively. The Harbury Works continued to
produce Lias lime products in addition to cement until 1939. The three rotary
cement kilns remained in service until manufacturing ceased in December 1970
and the site became a depot. In 1994 the remaining buildings were demolished
and the site cleared. The information on the cement work's was derived from
Dylan Moore's website 'Cement Plants and Kilns in Britain and Ireland'.
Details of the various locomotives that operated in the
Harbury Cement Works and quarries are given in the tables below:
Locomotive (Std.
Gauge) |
Type |
Manufacturer |
Works No |
Date |
Acquired |
Disposal |
No 5 Hawk |
0-4-0ST |
|
|
|
Ex A.R. Adams, Newport |
Scrapped circa 1933 |
No 7 |
0-4-0ST |
|
|
|
|
Scrapped before 1937 |
No 8 |
0-4-0ST |
Baguley Cars Ltd. Shobnall Rd,
Burton Rebuilt by Hudswell, Clarke & Co Ltd. Leeds |
No 621 |
1919 1928 |
Ex Thomas Salt & Co, Burton
1928 |
|
Whitby No 9 |
0-4-0ST |
Peckett & Sons Ltd. Atlas
Locomotive Works, Bristol |
No 1505 |
1918 |
Ex Ellesmere Port Works C1933 |
|
Cunarder |
0-6-0ST |
Hunslet Engine Co Ltd. Leeds |
No 1690 |
1931 |
March 1957 |
April 1969 acquired for
preservation |
|
|
|
|
|
|
|
Locomotive (3
Gauge) |
Type |
Manufacturer |
Works No |
Date |
Acquired |
Disposal |
No 1 Hawk |
0-4-2ST |
Kerr Stuart & Co Ltd. California
Works, Stoke on Trent |
No 1213 |
1914 |
|
To Holborough Cement Co. |
No 2 Lark |
0-4-0ST |
Hunslet Engine Co Ltd. Leeds |
No 704 |
1904 |
Ex Sir Robert McAlpine |
Scrapped circa 1938 |
No 3 Eagle |
0-4-0ST |
Peckett & Sons Ltd. Atlas
Locomotive Works, Bristol |
No 1654 |
1924 |
|
Scrapped prior 1947 |
No 4 |
0-4-0ST |
Peckett & Sons Ltd. Atlas
Locomotive Works, Bristol |
No 1663 |
1924 |
|
Scrapped prior 1947 |
No.6 |
0-4-0ST |
Peckett & Sons Ltd. Atlas
Locomotive Works, Bristol |
No 1720 |
1926 |
|
Scrapped prior 1947 |
No 12 |
0-4-0¹ |
Sentinel Waggon Works (1936)
Ltd. Shrewsbury |
No 6255 |
|
New |
Derelict 1945 |
No 13 |
0-4-0¹ |
Sentinel Waggon Works (1936)
Ltd. Shrewsbury |
No 6256 |
|
New |
Derelict 1943 |
No 3 |
0-4-0¹ |
Sentinel Waggon Works (1936)
Ltd. Shrewsbury |
No 6257 |
|
New |
Derelict 1937 |
Note¹ - Vertical cylinders, geared transmission
Two 3 gauge 2-4-0 Diesel locomotives were purchased
from John Fowler & Co (Leeds) Ltd. in 1933. The Harbury Cement Works
also had a 111½ gauge railway operated by five Simplex 4
wheel petrol locomotives (at least two of which were ex War Department). By
1946, this narrow gauge track had been removed and all stock was derelict.
Robert Ferris
On the GWR mainline
Views of Harbury Cement Works and locomotives
Great Western Railway Appendix to No 13 Section of
the Service Time Tables March 1929 and until further notice |
GREAVES SIDINGS SOUTHAM ROAD AND
HARBURY 1 Messrs Greaves, Bull and Lakin perform their shunting work at
this place with a private engine accompanied by a shunter employed by the firm.
The engine works into and out of the two Sidings set apart for the firms
traffic situated on the Down Side of the line. 2 The engine must cease
operations in the Sidings referred to when requested by the Great Western
Signalman or Shunter to do so for a GW train to work. 3 There are Up and
Down Main Line connections. One of the Sidings extends at the north end into
the Down Goods Running Loop. 4 A swing block over both rails of this Siding
is provided clear of the connection from the Down Main Line to the Goods
Running Loop, and, when not in use, the swing block must be placed across the
Siding rails and secured in that position by padlock, the key of which must be
kept in Greaves Siding Signal Box. 5 When it is necessary to remove the
swing block for shunting purposes, the GW Guard or Shunter must obtain the key
of the padlock from the Signal Box, and after the work is completed, the man
returning the key to the Signal Box will be responsible for seeing that all
vehicles are clear inside the swing block and that the latter is padlocked
across the Siding. 6 Messrs Greaves, Bull and Lakins men must not b
allowed in any circumstances to have possession of the key or interfere in any
way with the swing block. 7 During the time the key of the padlock is out
of the Signal Box no train must be diverted to the Down Goods Running Loop
without a clear understanding between the Signalman and the Guard performing
the shunting operations. 8 Guards of trains calling to put off or pick up
at these Sidings must satisfy themselves that all is clear before commencing
operations, and have a clear understanding with the man in charge of the
firms engine if it is about.
STATION TRUCK TRAFFIC FOR GREAVES
SIDINGS
Up Traffic Whenever there are
articles in the Station Truck sent by the 8.25 am ex Bordesley Junction and
there are any of Greaves, Bull & Lakins wagons on the train, the
articles must be transhipped at Harbury into one of that firmss empty
lime wagons going into the Works. Should there be no such wagon on the train,
the traffic must be put out at Harbury and afterwards loaded in one of Greaves,
Bull & Lakins wagons going into the sidings. Down Traffic
One of Greaves, Bull & Lakins empty wagons to be kept back at
Banbury for this Train, and the traffic for Greaves Works transhipped
into it; should this not be possible at any time then traffic must be put out
at Harbury Station, and sent to Greaves Works. The Goods Agents at Banbury
and Harbury must see the wagons so used are properly labelled and the invoices
and Station Truck lists duly marked showing transfer into wagon going to
Greaves, Bull and Lakins Works. The Guards, must, however take
advantage of any lengthened wait at intermediate Stations to effect the
transfer before reaching Harbury or Banbury.
Record of Wagons attached and detached at
Greaves Sidings. A list giving particulars of traffic attached and
detached at Southam Road, must be prepared by the Guard of the trains which
call at these Sidings. The Guards of Down Trains must hand the list to the
Station Master at Southam Road. The Guards of Up Trains must hand the list
to the Station Master at Fenny Compton, who must forward it to the Southam Road
Station Master.
Specific Engine Whistles at Greaves
Siding Main to Loop .. .. .. .. .. .. 2 Whistles
ROLLING STOCK WORKED INTO PRIVATE
SIDINGS The undermentioned restrictions in regard to Rolling Stock
worked into Private Sidings are in operation, and must be observed by all
concerned: At Southam Road Station Greaves Siding All but
four wheeled stock of ordinary dimensions are prohibited.
List of Special Advices to be sent from various
places to the Traffic Controller: Greaves Siding Signal Box
Information is to be sent by Checker Particulars of traffic requiring
clearance from Private Sidings.
SUSPENDING SHUNTING MOVEMENTS WHILST
PASSENGER TRAINS PASS Before the Signals are lowered for Passenger
Trains any of the following Shunting movements must be suspended, and the
Shunter or Guard told not to move the vehicles until the Passenger Train has
passed. The Signalman must give the cease shunting order and see
that it is obeyed in time to enable the Signals to be lowered for the Passenger
Train without causing delay to it. At Greaves Siding Signal Box when
Passenger Train passing: On Up Main Shunting movements to be
stopped are Down Main to Down Sidings or setting back to rear of Train standing
on Down Main. On Down Main Shunting movements to be stopped
are setting back to rear of Train standing on Up Main.
|