 |
London North Western
Railway:
 Midland
Railway:
 Stratford
Midland Junction Railway
|

|
LMS Route: Evesham to Birmingham
Cofton Tunnel: mrcof1669
 |
The entrance to Cofton tunnel can be seen beneath the early
stages of the cutting being widening in the summer of 1928. A P&W Hut can
be seen half way up the embankment with a footpath to the top. The location of
the hut is most likely to be because of the ground conditions - the only place
a building could be erected near to the track as faults plagued the
construction of the tunnel and the widening of the cutting. The process of
removing the tunnel and widening the cutting began with removal of the earth to
one side of the tunnel, suitably angled, together with the soil above the
tunnel. Once the top of the tunnel had been reached the section to the side was
taken down further - immediately adjacent to the tunnel - so a concrete
retaining wall could be built (see image see image 'mrcof1666'). Meanwhile on the other side of the
cutting, where the extra tracks were to go, the earth was also removed, down to
the top of the tunnel. At this point temporary (contractors) tracks were laid
so that travelling steam cranes and wagons could run the length of the tunnel.
Then, over the weekend of 26th to 18th January 1929, the tracks within the
tunnel were protected by sleepers laid over the top allowing the brickwork to
be dropped on top. The steam cranes then would lower square timber hoppers for
the men to load the rubble in to and then lift these to be loaded into the
contractors wagons to be taken away (see image 'mrcof1671'). Once all of the tunnel brickwork had been
removed then the remaining earth to the side of the tunnel would be excavated
until the cutting was at the required depth.
back

|