|
|
Handsworth and Smethwick Station
Handsworth & Smethwick station opened for passengers on
14th November 1854 as an intermediate station on the Birmingham Wolverhampton
& Dudley Railway (BW&DR), which became part of the Great Western
Railway's northern main line as they strived to reach Liverpool. At the height
of the Railway Mania on 3rd August 1846, the nominally independent BW&DR
received the Royal Assent to an Act of parliament which authorised construction
of a railway for £700,000, from Snow Hill Station in Birmingham to a
junction with the Oxford, Worcester and Wolverhampton Railway (OWWR) at
Priestfield, from where they would have running rights over two miles of OWWR
track to Wolverhampton. The same Act authorised the BW&DR to also build a
short branch from their new line at Swan Village to a junction with the South
Staffordshire Railway (SSR) at Great Bridge from where they would have running
rights over the SSR to Dudley, thereby enabling a second connection to be made
with the OWWR. Although intended to be broad gauge the Gauge Act prevented this
and the BW&DR initially planned to amalgamate with the Birmingham and
Oxford Junction Railway (B&OJR) to form a larger independent concern, but a
shareholders proposal to sell the line to the Great Western Railway resulted in
a second parliamentary bill on 31st August 1848 which allowed the purchase of
the BW&DR and authorised the laying of broad gauge track. This did not
include the Dudley branch, as the gauge on this section of line had been
specified in original 1846 Act to be identical as that on the SSR. Construction
of the BW&DR was delayed, while the Great Western Railway unsuccessfully
negotiated with the LNWR for running rights over their Stour Valley Railway,
but was eventually started in 1851. The appointed Engineer was John Robinson
McClean, who was also Engineer for the SSR, the final section of which (Walsall
to Dudley) had been approved by the Board of Trade (BoT) on 11th April 1850 and
opened for passenger traffic on 1st May. John McClean's influence can be seen
in the railway's architecture and a distinctive rigid block-like style is
evident in the station buildings, with that at Handsworth & Smethwick being
almost exactly the same as those at Wednesbury and West Bromwich.
Apart from the seven stations the principle engineering
features were three tunnels; one of 412 yards long north of Swan Village and
two short ones (135yards and 160 yards) amongst the imposing brick lined
cuttings between Birmingham and Hockley. The railway was laid as mixed gauge
double track, allowing the broad gauge to be extended north to Wolverhampton
and trains from the recently acquired railways to Shrewsbury and Chester to
reach Birmingham and eventually Paddington. On 25th August 1854 Captain Douglas
Galton from the BoT inspected the line prior to giving approval, but the
following day the 63 foot span wrought-iron tubular girder bridge over the
Winson turnpike road (Handsworth New Road) collapsed shortly after a locomotive
with two ballast wagons had crossed over it. The Great Western Railway asked
Brunel to inspect the line and he condemned another five bridges as being too
weak and these were replaced or strengthened over the next two months. Once
this work had been completed the line was approved by the BoT and opened on
14th November 1854. At Handsworth & Smethwick station a goods yard with a
large goods shed (see image 'qwrhs2645') was
constructed adjacent to the Down line. The Stourbridge Extension Railway was
completed on 1st April 1867 joining the BW&DR at Handsworth Junction (1,100
yards north of Handsworth & Smethwick Station) and this increased traffic.
The broad gauge passenger services had ceased on 1st November 1864 and the
third rail was removed from the line by 1st April 1869. In 1892 an up refuge
siding was provided at Handsworth & Smethwick and this was subsequently
converted into a loop with its entrance at Handsworth Junction in 1899. In the
goods yard four additional sidings increased capacity and provided a mileage
yard, while at the Birmingham end of the station a pair of long sidings were
established on either side of the main line. The quantity of traffic required a
goods shunting engine to be sent daily from Bordesley shed and in 1906 this is
recorded as arriving at Handsworth at 5:55am and leaving at 3:35pm.
On 19th December 1909 major improvements to the line between
Snow Hill and Handsworth Junction were completed with the track quadrupled,
stations rebuilt and new signal boxes provided. At Handsworth & Smethwick
station the original up platform was extended to 543 feet, with a new 493 foot
long double sided island platform and 473 foot long down relief platform
provided. Access to the new platforms was by a footbridge and both the new
platforms had a waiting room, ladies waiting room with toilet and a gentlemen's
toilet under a wide canopy. At the Handsworth Junction end of the station new
cattle pens and a loading bank capable of accommodating eleven wagons were
constructed on the up side behind the new Handsworth North Signal box, although
by 1921 these sidings were called the carriage dock sidings and eight wheeled
stock was prohibited (indicating that they was probably used for loading and
unloading fitted vehicles suitable for travelling in passenger trains, ie brown
stock). On the down side a connection was made to the Birmingham Railway
Carriage & Wagon Co (BRCW) private railway network (see image 'misc/brc&wc_works'). On the Birmingham
side of the station beyond the new Handsworth South Signal box, an extensive
marshalling yard at Queen's Head Sidings was provided (see image 'gwrqhy2004'), which included two refuge loops capable
of holding sixty wagons and fifty seven wagons on the up and down sides
respectively.
Following the sale of a Tramway Power Station located a
short distance away in Downing Street to the Shropshire, Worcestershire &
Staffordshire Electric Power Co in 1908 and subsequent installation of modern
AC generator plant, public electricity supplies became available in the area
and in 1922 a three ton jib crane in the goods shed and the six ton jib crane
in the mileage yard were both electrified. In this mileage yard additional
mileage sidings were also laid out increasing the capacity of this area to
accommodate a total of 99 wagons. The adjacent original goods yard together
with the goods shed could hold a further 110 wagons. In 1926 the transfer
capacity of the goods facilities was increased with the addition of a covered
external platform extension to the goods shed (see image 'gwrhs2641').
In 1927 the two long ladder crossings at the north end of
the station were removed allowing the Handsworth North Signal Box to be closed
on 4th March 1928. Additional track circuits were provided and two new ground
frames, electrically released from the South Box (renamed Handsworth
& Smethwick Signal Box) were established to cater for the remaining
switches to sidings at this end of the station. The levers in the two ground
frames were:
Handsworth Station Ground Frame No 1
Interlocking Lever No 2 For points between Up main and
sidings
Handsworth Goods Yard Ground Frame No 1
Interlocking Lever No 2 For spring points in Down relief line No 3
For disc Down relief line to sidings No 4 For points in
siding No 5 For disc sidings to Down relief line
In 1929 the Handsworth & Smethwick and Queen's Head
yards had 69 goods staff employed between them and goods traffic in 1937
totalled 189,537 tons (66,000 tons of which was coal and coke). In the second
world war the railway infrastructure in Birmingham was targeted by German
air-raids and on the night of the 11-12th December 1940 the goods shed was
destroyed by a landmine, killing three staff and three horses (see image 'gwrhs2635').
The two lever ground frame controlling the access from the
up main line to the cattle pens and carriage dock sidings was taken out of use
on 25th March 1957 and these sidings were subsequently removed. Gradually other
services were rationalised as demand decreased, with the facilities and sidings
closing. The BRCW connection was removed in March 1965 and all the goods
facilities were closed on 9th September 1968. The station closed, along with
all passenger services on the line on 6th March 1972. The main line track was
removed in September 1972, but some sidings were retained in the Goods and
Mileage yard as private sidings for Cooper's Metals, while both relief lines
were retained to give access to these, an engineering siding, plus the private
sidings in the former Queen's Head yard and Soho & Winson Green yard.
Handsworth & Smethwick Signal Box remained open until 21st December 1975
after, which the relief lines were operated as two single lines.
Robert Ferris
Views of Handsworth and Smethwick Station
Locomotives seen at or near to Handsworth and Smethwick
Station
Ordnance Survey Maps & Diagrams
|