|
London North Western
Railway:
Midland
Railway:
Stratford
Midland Junction Railway
|
|
Kilsby Tunnel
Northamptonshire
Kilsby Tunnel is a railway tunnel on the London and
Birmingham Railway which was opened in 1838 and forms part of West Coast Main
Line railway. The tunnel is located near the village of Kilsby in
Northamptonshire approximately 5 miles south-east of Rugby and is 2,426 yards
in length. There are ten ventilating shafts each of nine feet in diameter, and
two large shafts of sixty feet diameter, these latter being surmounted by
impressive castellated towers . The tunnel took far longer, and cost
significantly more money to build than had been anticipated. This was because
the tunnel roof collapsed and the tunnel flooded unexpectedly due to quicksand
which trial borings into the hill had not revealed. The excess water from the
quicksand had to be pumped out, a process which took some eight months. This
shouldn't have been a complete surprise as similar problems were encountered
with nearby Blisworth tunnel on the Grand Union Canal a few decades earlier.
The length of time it took to build the tunnel delayed the opening of the
London and Birmingham Railway resulting in a stage coach service to be used to
move passengers between the two completed sections of the line. It took three
years, and cost £320,000 to build which was three times the original
estimate. It is reported that approximately 30 million bricks were used in
construction. Around the turn of the century the inner lining was giving cause
for concern, the remedy being to reline with Staffordshire blue brick. It was
designed and engineered by Robert Stephenson and it is today the 18th longest
tunnel on the British railway system.
The construction of the tunnel has been recorded by Samuel
Smiles in his 1879 autobiography of the Stephenson's. The section relevant to
the tunnel, pages 246 to 252, is provided below.
LIVES of the ENGINEERS GEORGE AND ROBERT
STEPHENSON
BY SAMUEL SMILES (1879)
Though not the largest, this is in many respects one of the
most interesting works of the kind in England. It is about 2400 yards long, and
runs at an average depth of about 160 feet below the surface. The ridge under
which it extends is of considerable extent, the famous battle of Naseby having
been fought upon one of the spurs of the same high ground about seven miles to
the eastward.
Previous to the letting of the contract, the character of
the underground soil was examined by trial-shafts. The tests indicated that it
consisted of shale of the lower oolite, and the works were let accordingly. But
they had scarcely been commenced when it was discovered that, at an interval
between the two trial-shafts which had been sunk, about 200 yards from the
south end of the tunnel, there existed an extensive quicksand under a bed of
clay 40 feet thick, which the borings had escaped in the most singular manner.
At the bottom of one of these shafts the excavation and building of the tunnel
were proceeding, when the roof at one part suddenly gave way, a deluge of water
burst in, and the party of workmen with the utmost difficulty escaped with
their lives. They were only saved by means of a raft, on which they were towed
by one of the engineers swimming with the rope in his mouth to the lower end of
the shaft, out of which they were safely lifted to the daylight. The works were
of course at that point immediately stopped.
The contractor, who had undertaken the construction of the
tunnel, was so overwhelmed by the calamity, that, though he was relieved by the
Company from his engagement, he took to his bed and shortly after died.
Pumping-engines were then erected for the purpose of draining off the water,
but for a long time it prevailed, and sometimes even rose in the shaft. The
question then presented itself, whether in the face of so formidable a
difficulty, the works should be proceeded with or abandoned. Robert Stephenson
sent over to Alton Grange for his father, and the two took serious counsel
together. George was in favour of pumping out the water from the top by
powerful engines erected over each shaft, until the water was mastered. Robert
concurred in that view, and although other engineers pronounced strongly
against the practicability of the scheme and advised its abandonment, the
directors authorised him to proceed; and powerful steam-engines were ordered to
be constructed and delivered without loss of time.
In the mean time, Robert suggested to his father the
expediency of running a drift along the heading from the south end of the
tunnel, with the view of draining off the water in that way. George said he
thought it would scarcely answer, but that it was worth a trial, at all events
until the pumping-engines were got ready. Robert accordingly gave orders for
the drift to be proceeded with. The excavators were immediately set to work;
and they were very soon close upon the sand bed. One day, when the engineer,
his assistants, and the workmen were clustered about the open entrance of the
drift-way, they heard a sudden roar as of distant thunder. It was hoped that
the water had burst infor all the workmen were out of the drift,and
that the sand bed would now drain itself off in a natural way. Instead of
which, very little water made its appearance; and on examining the inner end of
the drift, it was found that the loud noise had been caused by the sudden
discharge into it of an immense mass of sand, which had completely choked up
the passage, and prevented the water from flowing away.
The engineer now found that there was nothing for it but to
sink numerous additional shafts over the line of the tunnel at the points at
which it crossed the quicksand, and endeavour to master the water by sheer
force of engines and pumps. The engines erected, possessed an aggregate power
of 160 horses; and they went on pumping for eight successive months, emptying
out an almost incredible quantity of water. It was found that the water, with
which the bed of sand extending over many miles was charged, was to a certain
degree held back by the particles of the sand itself, and that it could only
percolate through at a certain average rate. It appeared in its flow to take a
slanting direction to the suction of the pumps, the angle of inclination
depending upon the coarseness or fineness of the sand, and regulating the time
of the flow. Hence the distribution of the pumping power at short intervals
along the line of the tunnel had a much greater effect than the concentration
of that power at any one spot. It soon appeared that the water had found its
master. Protected by the pumps, which cleared a space for the engineering
operationscarried on in the midst, as it were, of two almost
perpendicular walls of water and sand on either sidethe workmen proceeded
with the building of the tunnel at numerous points. Every exertion was used to
wall in the dangerous parts as quickly as possible; the excavators and
bricklayers labouring night and day until the work was finished. Even while
under the protection of the immense pumping power above described, it often
happened that the bricks were scarcely covered with cement ready for the
setting, here they were washed quite clean by the streams of water which poured
from overhead. The men were accordingly under the necessity of holding over
their work large whisks of straw and other appliances to protect the bricks and
cement at the moment of setting.
The quantity of water pumped out of the sand bed during
eight months of incessant pumping, averaged 2,000 gallons per minute, raised
from an average depth of 120 feet. It is difficult to form an adequate idea of
the bulk of the water thus raised, but it may be stated that if allowed to flow
for three hours only, it would fill a lake one acre square to the depth of one
foot, and if allowed to flow for one entire day it would fill the lake to over
eight feet in depth, or sufficient to float vessels of 100 tons. The water
pumped out of the tunnel while the work was in progress would be nearly
equivalent to the contents of the Thames at high water, between London and
Woolwich. It is a curious circumstance that notwithstanding the quantity thus
removed, the level of the surface of the water in the tunnel was only lowered
about 2½ to 3 inches per week, proving the vast area of the quicksand,
which probably extended along the entire ridge of land under which the railway
passed.
The cost of the line was greatly increased by the
difficulties encountered at Kilsby. The original estimate for the tunnel was
only £99,000; but before it was finished it had cost more than £100
per lineal yard forward, or a total of nearly £300,000. The expenditure
on the other parts of the line also greatly exceeded the amount first set down
by the engineer; and before the works were finished it was more than doubled.
The land cost three times more than the estimate; and the claims for
compensation were enormous. Although the contracts were let within the
estimates, very few of the contractors were able to complete them without the
assistance of the Company, and many became bankrupt.
The magnitude of the works, which were unprecedented in
England, was one of the most remarkable features in the undertaking. The
following striking comparison has been made between this railway and one of the
greatest works of ancient times. The Great Pyramid of Egypt was, according to
Diodorus Siculus, constructed by 300,000according to Herodotus, by
100,000men. It required for its execution twenty years, and the labour
expended upon it has been estimated as equivalent to lifting 15,733,000,000 of
cubic feet of stone one foot high. Whereas, if the labour expended in
constructing the London and Birmingham Railway be in like manner reduced to one
common denomination the result is 25,000,000,000 of cubic feet more than was
lifted for the Great Pyramid; and yet the English work was performed by about
20,000 men in less than five years. And whilst the Egyptian work was executed
by a powerful monarch concentrating upon it the labour and capital of a great
nation, the English railway was constructed, in the face of every conceivable
obstruction and difficulty, by a company of private individuals out of their
own resources, without the aid of Government or the contribution of one
farthing of public money.
The labourers who executed this formidable work were in many
respects a remarkable class. The railway navvies, as they are
called, were men drawn by the attraction of good wages from all parts of the
kingdom; and they were ready for any sort of hard work. Some of the best came
from the fen districts of Lincoln and Cambridge, where they had been trained to
execute works of excavation and embankment. These old practitioners formed a
nucleus of skilled manipulation and aptitude, which rendered them of
indispensable utility in the immense undertakings of the period. Their
expertness in all sorts of earthworks, in embanking, boring, and
well-sinkingtheir practical knowledge of the nature of soils and rocks,
the tenacity of clays, and the porosity of certain stratificationswere
very great; and, rough-looking though they were, many of them were as important
in their own department as the contractor or the engineer.
During the railway-making period the navvy wandered about
from one public work to anotherapparently belonging to no country and
having no home. He usually wore a white felt hat with the brim turned up, a
velveteen or jean square-tailed coat, a scarlet plush waistcoat with little
black spots, and a bright-coloured kerchief round his herculean neck, when, as
often happened, it was not left entirely bare. His corduroy breeches were
retained in position by a leathern strap round the waist, and were tied and
buttoned at the knee, displaying beneath a solid calf and foot encased in
strong high-laced boots. Joining together in a butty gang, some ten
or twelve of these men would take a contract to cut out and remove so much
dirtas they denominated earth-cuttingfixing their price
according to the character of the stuff, and the distance to which
it had to be wheeled and tipped. The contract taken, every man put himself on
his mettle; if any was found skulking, or not putting forth his full working
power, he was ejected from the gang. Their powers of endurance were
extraordinary. In times of emergency they would work for 12 and even 16 hours,
with only short intervals for meals. The quantity of flesh-meat which they
consumed was something enormous; but it was to their bones and muscles what
coke is to the locomotivethe means of keeping up the steam. They
displayed great pluck, and seemed to disregard peril. Indeed the most dangerous
sort of laboursuch as working horse-barrow runs, in which accidents are
of constant occurrencehas always been most in request amongst them, the
danger seeming to be one of its chief recommendations.
Working, eating, drinking, and sleeping together, and daily
exposed to the same influences, these railway labourers soon presented a
distinct and well-defined character, strongly marking them from the population
of the districts in which they laboured. Reckless alike of their lives as of
their earnings, the navvies worked hard and lived hard. For their lodging, a
hut of turf would content them; and, in their hours of leisure, the meanest
public-house would serve for their parlour. Unburdened, as they usually were,
by domestic ties, unsoftened by family affection, and without much moral or
religious training, the navvies came to be distinguished by a sort of savage
manners, which contrasted strangely with those of the surrounding population.
Yet, ignorant and violent though they might be, they were usually good-hearted
fellows in the mainfrank and openhanded with their comrades, and ready to
share their last penny with those in distress. Their pay-nights were often a
saturnalia of riot and disorder, dreaded by the inhabitants of the villages
along the line of works. The irruption of such men into the quiet hamlet of
Kilsby must, indeed, have produced a very startling effect on the recluse
inhabitants of the place. Robert Stephenson used to tell a story of the
clergyman of the parish waiting upon the foreman of one of the gangs to
expostulate with him as to the shocking impropriety of his men working during
Sunday. But the head navvy merely hitched up his trousers, and said, 'Why,
Soondays haint cropt out here yet!' In short, the navvies were little
better than heathens, and the village of Kilsby was not restored to its wonted
quiet until the tunnel-works were finished, and the engines and scaffoldings
removed, leaving only the immense masses of débris around the line of
shafts which extend along the top of the tunnel.
In illustration of the extraordinary working energy and
powers of endurance of the English navvies, we may mention that when
railway-making extended to France, the English contractors for the works took
with them gangs of English navvies, with the usual plant, which included
wheelbarrows. These the English navvy was accustomed to run out rapidly and
continuously, piled so high with stuff that he could barely see
over the summit of his load, the gang-board along which he wheeled his barrow.
While he thus easily ran out some 3 or 4 cwt. at a time, the French navvy was
contented with half the weight. Indeed, the French navvies on one occasion
struck work because of the size of the English barrows, and there was an
émeute on the Rouen Railway, which was only quelled by the aid of the
military. The consequence was that the big barrows were abandoned to the
English workmen, who earned nearly double the wages of the Frenchmen. The
manner in which they stood to their work was matter of great surprise and
wonderment to the French people, who came crowding round them in their blouses,
and, after gazing admiringly at their expert handling of the pick and mattock,
and the immense loads of dirt which they wheeled out, would exclaim
to each other, 'Mon Dieu, voila! voila ces Anglais, comme ils
travaillent!'.
Construction of Kilsby Tunnel
Kilsby Tunnel at work
Ordnance Survey maps and Signalling Diagrams
If you are wondering as to why Kilsby Tunnel has been
included on a website dedicated to Warwickshire's railways, its because: a) we
have a policy of starting and finishing each route with a significant station
or location and Kilsby is certainly the latter; and b) as a child when I
travelled by steam locomotive to Euston I was always mightly impressed by its
length and massive ventilation towers; and c) as its my website I can say 'why
not!!!!'
|